Problem |
The building of Petar Kocic Elementary School was dilapidated.
Improper hydro-insulation damaged the facilities. Window frames were
rotten so that windows could not seal properly, which resulted in
loss of heating energy. Also the floors in the classrooms were very
old and damaged. |
|
Solution |
Renovation works included replacing windows and doors; repairing the
floors in all the classrooms by sanding and varnishing them; and
painting the walls in the new building. |
|
Impact |
Children and teachers now enjoy improved conditions for regular
classes and after-school activities. Also, heating costs have been
reduced. |
|
Beneficiaries |
1,059 |
|
USAID Funds |
$65,882 |
|
Community and Other
Contribution |
$52,400 |
|